June 4, 2025 Agenda
June 4, 2025 Minutes
June 4, 2025 Video
The Feasibility Study Committee met on June 4, 2025 to review community feedback, explore design models, and continue narrowing options for the future of Pomperaug Elementary (PES) and Gainfield Elementary (GES).
π PES/GES Feasibility Study Committee Meeting Presentation June 4, 2025
Key highlights:
The June 4, 2025, Feasibility Study Committee Meeting presentation served as a critical update, leveraging community feedback and technical analysis to narrow the focus to three prioritized options for the future of Gainfield Elementary School (GES, built 1941) and Pomperaug Elementary School (PES, built 1967)
The presentation affirmed that the resulting Top 3 Options prioritize new construction and a district-wide approach, based on the Committee's aim to resolve existing conditions and determine the best long-term value for taxpayers.
Key Findings and Rationale
- Value Analysis (New Construction vs. Renovate as New): Although the State reimbursement rate is higher for Renovate-as-New (RNV) (48.93%) than for New Construction (38.93%), a detailed value analysis showed that New Construction often offers the best overall value. RNV options incur substantial "Value Lost" costs that do not stay in the building, such as costs for temporary facilities, premiums for occupied renovations, and significant escalation due to a longer construction timeline (up to 48 months vs. 18-24 months for new construction)
- "School Within a School" Concept: To address community concerns about maintaining a small-school feel within a combined facility, the Committee explored the "School Within A School" concept, using Barnum Elementary in Cheshire, CT, as a case study. This design allows one new facility to be conceptually divided into separate, small learning communities (e.g., PK-2 and 3-5)
- Community Feedback: A recap of Community Conversation #3 confirmed community interest in future-proofing, addressing capacity (including the potential impact of the IBM site conversion), Pre-K planning, and the economies of scale offered by a combined appraoch.
The Top 3 Preferred Options
The three options moving forward all involve new construction and district-wide enrollment planning, including the relocation of 100 students from Long Meadow Elementary School (LMES) and the incorporation of an 80-student Pre-K program.
3d: Combined New School @ TBD (Largest): One new building for 1,008 students
Total Project Cost $147 Million
Estimated Cost to Region 15: $78 Million
4c: Two New Schools (Larger Enrollment): Two new buildings (New PES & New GES), each for 504 students
Total Project Cost: $163 Million ($83M + 80M)
Estimated Cost to Region 15: $85 Million ($44M + $42M)
4b: Two New Schools (Smaller Enrollment): Two new buildings, each for 504 students (P) on existing sites
Total Project Cost: $166 Million ($85M + 80M)
Estimated Cost to District: $87 Million ($45M + $42M)
Next Steps
The Committee's final goal for this phase is to select a preferred option by late summer. Next steps include:
- Refining and selecting a preferred option.
- Refining the budget and developing detailed cost impact reports.
- Continuing community conversation and engagement.
- Preparing the necessary Grant Application for the June 2026 deadline
Please note that this is an overview summarizing the key points of the meeting minutes and facility study presentations. For complete information, including specific details, references, data tables, and in-depth discussions, you should consult the full report and watch and listen to the Board of Education (BOE) meeting.